AI Data Centers Face a Voter Revolt

· Summarized

Share this episode
Anyone with this link can open it.
Share Link
Start at 0:00

Key takeaways

  • Data-center opposition influenced 56% of voters’ congressional choices, according to exit polling, and helped anti-data-center candidates win in several major AI-development states.
  • The opposition is unusually bipartisan and often organized by local Facebook groups, reflecting concerns about electricity, water, property values, and the physical visibility of AI infrastructure.
  • Projects already under construction will probably proceed because moratoria generally do not apply retroactively; planned projects, especially in Texas, face the greatest uncertainty.
  • AI companies may shift construction to other U.S. states or abroad, but finding land, arranging power, and rebuilding infrastructure could delay their targets.
  • Because data centers account for much of current construction growth and are projected to represent about 2% of GDP in 2026, a prolonged slowdown could affect employment and suppliers beyond the technology sector.

Summary

Voters reject data centers at the ballot box

Host Julie Chang says opponents of the data centers powering the AI boom won sweeping victories this week. WSJ reporter Will Parker explains that voters in towns across Ohio, Illinois, Kansas, and Florida were directly asked whether they wanted data centers and, in almost every case, said no. Data centers also became a campaign issue in gubernatorial, Senate, and House races, with many candidates running on skeptical or explicitly anti-data-center platforms and winning.

Anti-data-center candidates win in major development states

Parker highlights victories by Texas governor-elect Gina Hinojosa, who asked whether Texas was “a state by and for the people” or “the billionaire’s world,” Ohio Democrat Amy Acton, and Georgia’s Keisha Lance Bottoms; Michigan also elected a governor after a data-center-focused race. Texas, Ohio, and Georgia are among the busiest states for AI construction, with development around Atlanta especially concentrated. Exit polling found that 56% of voters considered data centers an important factor in their choices for Congress.

Why opposition spread beyond neighboring communities

Parker says data-center opposition is broader, more geographically dispersed, and more bipartisan than earlier fights over factories, pollution, fracking, housing, or density. Facebook groups often mobilize people who were not previously political, driven by concerns about electricity costs, water use, and home values in suburban and exurban areas. He adds that a data center is the visible, physical manifestation of otherwise abstract anxiety about AI, giving people something they can see and oppose even when Silicon Valley software and chatbots are harder to confront.

Projects already under construction probably will continue

Asked whether the election results would halt construction, Parker says “probably not.” Moratoria generally do not affect projects already underway, and a large amount of construction is in its early stages. The bigger uncertainty concerns planned projects, particularly in Texas. Texas, Ohio, and Georgia together account for about 40% of total data-center development, and Parker says a state moratorium could delay Texas’s buildout by a year, 18 months, or another undetermined period.

Tech companies may move elsewhere, but relocation takes time

Shares of Intel, AMD, and other companies connected to the data-center buildout continued to slide after the election, amid uncertainty about state policies, company debt, and financing. Parker reports that OpenAI discussions began on election night about whether the company could meet its construction targets, while Anthropic’s S-1 mentioned exploring opportunities outside the U.S. because of opposition. He cautions that if a few states close to data centers, companies can seek other states, although buying land and securing power takes time.

A slowdown could reach construction and GDP

Parker says data centers have become the main source of growth in construction while office, housing, and apartment construction has stagnated or declined. A slowdown could reduce construction employment and affect suppliers of HVAC equipment and other building inputs, though he sees no immediate reason to expect one because so much work is already underway. Goldman Sachs projects data-center construction will equal about 2% of GDP in 2026—comparable, according to estimates Parker cites, to the contribution of railroads during the 19th century. He will watch whether more states and towns follow Texas, Ohio, and Georgia.

Sponsors

  • McKinsey & Company · McKinsey senior partner Tanguy Katlan describes AI moving from screens into the physical world, including robotics, engineering, and space travel. He says leaders should assess McKinsey’s 14 technology trends in their own business context rather than chase headlines, redesign end-to-end workflows around proprietary data, and rewire operating models. The ad also names autonomy, absorption speed, cybersecurity, chip-and-model co-design, and grid and energy capacity as key themes.

Show notes

This week, voters across the country rejected data center expansion, backing ballot measures and candidates to ban or slow development. WSJ reporter Will Parker explains what this means for projects currently underway—and for the tech companies powering the AI boom. Julie Chang hosts.


Sign up for the WSJ's free Technology newsletter.


Hosted by Simplecast, an AdsWizz company. See pcm.adswizz.com for information about our collection and use of personal data for advertising.

Follow this show on AudioBrevity and new episodes get summarized for you. Create a free account

Couldn't load the audio. A blocker may be stopping the show's tracking links. Open the file